Crawfordsville Electric Reaches Rate Settlement

The Indiana Office of Utility Consumer Counselor (IURC) and Crawfordsville Electric Light & Power (CEL&P) have reached a settlement agreement (Cause No. 44684) in the utility’s pending rate case.   CEL&P, a municipal utility in the Hoosier State, serves about 10,000 customer accounts in Montgomery … Read more…

Vectren Loses Indiana Appeal

The Indiana Court of Appeals on October 29 struck down (Case No. 93A02-1502-EX-110) approval of Vectren’s plan to spend roughly $90 million in ratepayer money on its aging A.B. Brown and F.B. Culley coal-fired power plants outside Evansville, Indiana. The court found that the Indiana … Read more…

Explosive IPL Rate Case Continues This Week

The Indiana Utility Regulatory Commission (IURC Cause Nos. 44576, 44602) will continue hearing testimony this week on a rate request first made by Indianapolis Power & Light (IPL) last December – and delayed from March until September 21 by the vigorous objections of the Indiana … Read more…

User Name :
Password :
 
If you've no account register here first time
User Name :
User Email :
Password :

Login Now